The
project cost is estimated as 300 million Dollars,
of which 240 million Dollars (80%) will be
financed by loan and 60 million Dollars by
contribution form the shareholders (20 %). Out of
the 240 million Dollars borrowing, The credit
facilities is expected to be extended on
non-recourse basis and secured by charges on all
assets of the Project Company and assignment of
all Project Agreements in favor of the
Lenders.
As a
condition precedent to drawing down the loan, the
shareholders may need to contribute upfront up to
50% of the base equity (30 million Dollars). This
initial base equity will be utilized to meet the
development activities, legal fees, payments to
various consultants, up-front payments Lenders,
and payment for preliminary works and milestones
completed by the EPC Contractor up to 4 to 5
months before of the first drawdown of loan
money.